  • Steel lead time slips past March start
    L: med · I: high
    open

    Mitigation: Confirm steel order by 25 Jan and get written lead-time commitment from fabricator.

  • Neighbour at no. 47 refuses party wall award
    L: low · I: high
    monitoring

    Mitigation: Surveyor briefed. Meeting arranged for 15 Jan to walk through the works.

  • Budget overrun on kitchen fit-out
    L: med · I: med
    open

    Mitigation: Cap kitchen at £22k; get two more quotes before committing.

  • Trees at boundary may need a TPO check
    L: low · I: med
    open

    Mitigation: Requested TPO search from council — response due 22 Jan.